You have to know the installation process and essentials of sanitary ware!

Internet + home improvement is on the rise, and the pockets of home improvement workers are starting to swell. I have long heard that home improvement workers have a one-month salary to kill ordinary white-collar workers. I have already made a small series and I am already eager to learn a technique. After all, "One skill is in hand, the world I have!"

If you want to have a home improvement, you must study hard and practice hard. There is no white lunch in the world! Compared with hardwear, sanitary ware, lamps, wallpapers, etc. are relatively easy, but during the installation process. There are also many details that need to be noted. Today, Xiaomei zooms in and shows you how to install the sanitary ware process and essentials. I don’t tell him the average person! If you are a layman, you want to get into the tens of thousands of months; if you are a worker, you want to improve yourself. Knowledge you have to know!

First, the sanitary ware installation process

Sanitary ware inlaid wall tiles → suspended ceiling → laying floor tiles → installing toilets, washbasins, bathtubs → installation and connection to drain pipes → installation of lamps, sockets, mirrors → installation of towel bars and other hardware accessories.

1. The process of the toilet

Check the ground drain pipe → align the nozzle → level the alignment → draw the mark → punch the hole → apply the putty → set the rubber pad → screw the nut → mark the two sides of the water tank → punch → insert Bolt → 捻 → → back water tank hanging flat to find positive → screw nut → install back water tank water elbow → install the eight-character door → bend the mother light fork → insert the drift door and the eight-word door → tighten the nut.

2, the process of the washbasin

Insert the expansion bolts → 捻 → → the tube rack is hung up → put the washbasin on the rack to find the level → water connection: washbasin → straighten → water connection.

3, the process of the tub

Bathtub installation: → water installation → putty closed tight → water installation → flattening

4, the shower process

Cold and hot water nozzles are flattened with test tubes → measure the size of the short section → install on the nozzle → shower copper inlet, lead and lead oil wrapped → nut tightened → fixed on the wall → upper copper tube installed in the three-way port → wood The screws are fixed to the wall.

5, the process of the bidet

Hybrid switch, door and nut of the hot and cold water door are leveled → the water gate is installed → the nozzle core door is installed → the hot and cold water door outlet nut is tightened → the nut on the mixing switch is tightened → three water door covers are installed → the magnetic basin is installed → When installing the nozzle → Install the water outlet → When installing the portable lever → Adjust the positioning.

Second, sanitary ware installation and construction essentials

1. Washing basin installation and construction essentials

(1) The washing basin product should be flat and non-destructive. The drain plug should have an overflow hole of not less than 8 mm in diameter.

(2) When the drain plug and the sink are connected, the overflow plug of the drain plug should be aligned with the overflow hole of the sink to ensure the smooth flow of the overflow. After the insert, the upper end of the drain plug should be lower than the bottom of the wash basin.

(3) The bracket fixing bolts can be galvanized bolts or galvanized metal expansion bolts of not less than 6mm (if the wall is porous brick, expansion bolts are strictly prohibited).

(4) After the washing basin is connected with the drain pipe, it should be firm and compact, and easy to disassemble. The joint should not be open. Silicone paste caulking is applied to the wash basin and wall contact.

(5) If the wash basin drain trap and faucet are plating products, the plating shall not be damaged during installation.

2, the installation of the bathtub essentials

(1) When installing the skirting tub, the bottom of the skirt should be close to the ground. The floor should be reserved for 250~300mm holes in the drainage area to facilitate drainage installation. The inspection hole is installed in the wall of the bathtub drainage end.

(2) Other types of bathtubs can determine the height of the upper surface of the bathtub according to relevant standards or user requirements. Then install the tub after laying two brick foundations. For example, if the side wall of the bathtub is built, the inspection hole should be set at the drain of the bathtub or the inspection hole should be opened on the wall of the drainage end.

(3) The height of all kinds of bathtub cold, hot water taps or mixing faucets should be higher than the plane above the bathtub 150mm, and the chrome plating layer should not be damaged during installation. The chrome cover should be in close contact with the wall.

(4) The height of the fixed shower and hose shower can be installed according to relevant standards or according to user requirements.

(5) The upper surface of the bathtub installation must be leveled with a horizontal ruler and must not be inclined. Apply a sealing paste to the side of the upper side of the bathtub and the wall.

(6) The connection between the bathtub drain and the drain pipe should be firm and compact, and it is easy to disassemble, and the joint should not be open.

3, the installation point of the toilet

(1) The installation angle of the water supply pipe is generally 250mm from the ground to the center of the angle valve. If the installation of the one-piece toilet should be based on the height of the water inlet of the toilet, but not less than 100mm, the center of the angle valve of the water supply pipe is generally sewage. 150mm to the left of the tube center or according to the actual size of the toilet.

(2) Low water tank toilet The water tank is fixed with galvanized bolts or with galvanized metal expansion bolts. If the wall is porous brick, it is strictly forbidden to use expansion bolts. Soft gaskets should be used between the water tank and the nut. It is strictly forbidden to use metal hard surface.

(3) With the water tank and the one-piece toilet, the back of the tank should be no more than 20mm away from the wall.

(4) The installation of the toilet is not less than 6mm galvanized expansion bolts, and the soft Gasket is fixed between the toilet and the nut. The sewage pipe should be exposed to the ground 10mm.

(5) When installing the toilet, first apply the putty around the bottom drain, then align the toilet outlet to the sewage pipe and slowly press it down to compact it, then tighten the gasket nut to remove the squeeze. Put out the putty, and clean it with a wire or a rag immediately after filling it with the putty around the base.

(6) The height of the overflow pipe in the flush tank should be 30~40mm below the wrench hole to prevent the water from overflowing from the wrench hole when the inlet valve is damaged.

Global hardware network

Concerned about surprises

Label: You have to know the installation process and essentials of sanitary ware!

Previous: Seven tips to teach you to identify environmentally friendly paints Next: Is the wall decoration paint good or wallpaper good?

STAINLESS STEEL PRODUCTS

Stainless steel is a corrosion resistant steel alloy with a minimum of 10% chromium. There are different grades and surface finishes of stainless steel produced to accommodate the environment in which the material will be implemented. Unlike carbon steel, stainless steel does not rust when exposed to air and moisture due to the sufficient amount of chromium present. The chromium creates an invisible passive film of chromium oxide that will not let oxygen attack the surface and prevents rusting of the iron base.

Yuhong Group is a stainless steel manufactory of more than 20 grades of Stainless Steel.

Stainless Steel Bright Annealed Tube

Stainless Steel Bright Annealed Tube,Bright Annealing Seamless Tube ,Bright Annealing Tube

YUHONG GROUP CO.,LIMITED , https://www.jessro-pipefittings.com