New Designed Hot Dipped Galvanized Modular Steel Structures

Model NO.: 3-208
Design Parameter: Wind Load, Snow Load and Earthquake
Service Offered: Design/Fabrication/Packing/Transport/Erection
Main Structure: Welded H Section/Lattice Structure/Tubular Parts
Quality Control: The Third Party, SGS, Asia Inspection All Accept
Transport Package: Using Container of 20 Feet and 40 Feet
Origin: China
HS Code: 7308900000
Model NO.: 3-208
Design Parameter: Wind Load, Snow Load and Earthquake
Service Offered: Design/Fabrication/Packing/Transport/Erection
Main Structure: Welded H Section/Lattice Structure/Tubular Parts
Quality Control: The Third Party, SGS, Asia Inspection All Accept
Transport Package: Using Container of 20 Feet and 40 Feet
Origin: China
HS Code: 7308900000
Company advantage:
1. We supply for Hyundai, SEPCOIII, Siemens etc.
Exported to more than 60 countries, with more than 200, 000 tons.
2. Biggest steel structure manufacturer in northern China, annual output 200, 000 tons.
Registered capital: USD 16million
120 engineers and 1260 staff in total.
3. ISO9000, ISO14000, ISO18000
American certificate system of CWI, AWS welder
European certificate system of EN-1090, EN welder
4. Our group is Canada listed company, total asset 4 billion, 3600 employees.


 
Performance is a hard truth
SN Project Name  Tons or Area
1 Steel structure for India JHARSUGUDA 9*135MW Power Plant 25,000 tons
2 First-stage project of India JHARSUGUDA 6*600MW Power Plant 24,000 tons
3 Steel structure for India BALCO 4*300MW Coal-firing Power Station 16,000 tons
4 Major workshop& ECR of 3*660MW, CLP Power Station, India 5500 tons
5 Steel structure for Nigeria Power Station Project 4000 tons 
6 Steel structure for  Vietnam  2*30MW Power Station Workshop 2100 tons 
7 Steel structure for  Indonesia  TANJUNGENIM 3*12MW Power Plant 1200 tons
8 India WPCL4*135 Coal-firing Power Station 3000tons 
9 Luli Group steel Making Workshop 11500 tons
10 Shoudu Iron and Steel company project, 2006 4100 tons
11 Steel Structure of Qingdao Laigang  Mansion , 33 floors, Heavy H Beam and Tubular Pillar 3600tons 
12 South Korean Hyundai Steel Project 2950 tons 
13 Steel Structure for Saudi Arabia HCP2*10000T/D cement plant 1600 tons
14 Philippines  Ship Company Main Workshop 3600 tons
15 Workshop of Deruibao Tires Company, project area 112,000SQM
16 1-5# Workshop of Huaxing Industrial Park, 2010, project area  86,000SQM

New Designed Hot Dipped Galvanized Modular Steel Structures

1. Data of the
Steel building ( made of modular steel structures ) :
Specification
Material : Grade Q235 , equivalent to ASTM A36
Grade Q345 , equivalent to ASTM A572
Section : Any product shape according to customer's requirements
Certification : ISO quality system , Chinese GB50221 - 2001
Sand Blast : SA 2.5 Sand blasting
Welding Technology : Single level butt welding , fillet welding by electric arc welding , 
and Gas shielded welding
Surface treatment : Hot dip galvanized , Epoxy zinc rich primer
Standard : ISO1461 ( 1999 ) , JIS H 8641 - 1999 , ASTM A 123 / A 123M-02
Welding Testing Ultrasonic Testing , X-ray Testing
Manufacturing Technology Drilling , Cutting , Assembling , Welding , Rectification , Testing etc

New Designed Hot Dipped Galvanized Modular Steel Structures

2. Brief of us:
We were founded in Shandong, which holds 100 million RMB registered capital. Our company is located in northern China, and it covers an area of 360, 000 square meter. Our company was specialized in the design and manufacture of steel structure workshop, high rise steel building, prefab building, and other related steel products. The products of our factory have always been wildly recognized by both abroad and domestic customers in the past ten years. In the year 2008, our company was officially designated as the main supplier of steel structure project by Shandong government. And our products that were exported to west Asia and South American etc were widely popular among our customers.
The main metal products designed and processed by our company include steel structure workshop, exhibition hall, civil structure building, high rise building, industrial steel structure for power plant, solar, oil& gas, chemical etc.

3. Project case- Industry Prefabricated Steel building:
Argentina prefabricated steel workshop project was done in the year of 2013, finished installation in the year of 2014. Total area of this workshop is 5, 700 square meters. Main workshop size is 84X 60X 9m, totally 4 spans, 15m per span with one 3ton crane in each, lifting height of the crane is 6m. Two accessory houses on both sides of the main workshop.
New Designed Hot Dipped Galvanized Modular Steel Structures

4. Hardware advantage for Steel building ( made of modular steel structures ) :
we are professional for designing and processing steel structure, prefab buildings, workshop, Steel building ( made of modular steel structures ) , and industrial& civil steel structure etc, you can confidently to place your project to us, and we can offer you with different structure options.
We have plenty of advanced production lines for steel structure and cladding structure, such as the world leading CNC cutting machine with cutting capacity of maximum thickness 200m and the maximum dimension 5m* 28m, which have the function for steel strip cutting and formation optional cutting; Large scale cutting saw can cut the profile for 1250mm, and the large scale three dimensional CNC drilling machine have the drilling capacity for H profile section area 1250mm; The large scale plan CNC drilling machine can drill the maximum 2m*1.6m with maximum thickness 100mm and maximum bore diameter 100mm;
New Designed Hot Dipped Galvanized Modular Steel Structures

5. Packing and Shipping for Steel building ( made of modular steel structures ) :
Packing Details:
1) For big single steel parts, no need to pack, just protect the end plate with blanket.
2) Main commonly frame: We possess the unique most professional and best packaging solution in China presently - framing package, which perfectly protects the structural steel members from any impact damage during the transport. Or according to customer' s requirement.
3) The cladding part: roof or wall single steel plate whose surface covered by transparent PVC, is wrapped by plastic film.
roof or wall sandwich panel without packing, will load into the container piece by piece, and then fixed firmly.

Shipping:
1) Main big frame will be shipped in bulk carrier
2) Other material load into 20ft( HQ) or / and 40ft( HQ)   
3) Cladding part: As our experience, 20ft closed container can be load around 450-500 square meters sandwich panel, but depends on the container is flat enough and the length of the panels. 40ft closed container can load around 900-1000 square meters in the same situations.
New Designed Hot Dipped Galvanized Modular Steel Structures

6. FAQ:
1) Price Term: FOB, CFR or CIF.
Shipping seaport: Qingdao Seaport. For FOB, CFR or CIF price, please specify which exact model steel building you need, and tell us your design data so that we can calculate the steel building cost, local transport charges and sea freight.

2) Payment: Typically 30% by T/ T as deposit, balance by T/ T before shipment. Other payment way can be negotiated.

3) Delivery: for 10000 SQM steel warehouse, goods can be ready for shipment about 1-2 months after receiving deposit.

4) How can I get a price for your Steel building ( made of modular steel structures ) ?
Please send us your drawing; we can according to your drawing give you one price.
Or, give us your design data, we will design and quote to you.

  Company advantage:
1. We supply for Hyundai, SEPCOIII, Siemens etc.
Exported to more than 60 countries, with more than 200, 000 tons.
2. Biggest steel structure manufacturer in northern China, annual output 200, 000 tons.
Registered capital: USD 16million
120 engineers and 1260 staff in total.
3. ISO9000, ISO14000, ISO18000
American certificate system of CWI, AWS welder
European certificate system of EN-1090, EN welder
4. Our group is Canada listed company, total asset 4 billion, 3600 employees.


 
Performance is a hard truth
SN Project Name  Tons or Area
1 Steel structure for India JHARSUGUDA 9*135MW Power Plant 25,000 tons
2 First-stage project of India JHARSUGUDA 6*600MW Power Plant 24,000 tons
3 Steel structure for India BALCO 4*300MW Coal-firing Power Station 16,000 tons
4 Major workshop& ECR of 3*660MW, CLP Power Station, India 5500 tons
5 Steel structure for Nigeria Power Station Project 4000 tons 
6 Steel structure for  Vietnam  2*30MW Power Station Workshop 2100 tons 
7 Steel structure for  Indonesia  TANJUNGENIM 3*12MW Power Plant 1200 tons
8 India WPCL4*135 Coal-firing Power Station 3000tons 
9 Luli Group steel Making Workshop 11500 tons
10 Shoudu Iron and Steel company project, 2006 4100 tons
11 Steel Structure of Qingdao Laigang  Mansion , 33 floors, Heavy H Beam and Tubular Pillar 3600tons 
12 South Korean Hyundai Steel Project 2950 tons 
13 Steel Structure for Saudi Arabia HCP2*10000T/D cement plant 1600 tons
14 Philippines  Ship Company Main Workshop 3600 tons
15 Workshop of Deruibao Tires Company, project area 112,000SQM
16 1-5# Workshop of Huaxing Industrial Park, 2010, project area  86,000SQM

New Designed Hot Dipped Galvanized Modular Steel Structures

1. Data of the
Steel building ( made of modular steel structures ) :